Wagon Wheel Trail La Crescent to La Crosse: The 2027–2028 Outlook

The Wagon Wheel Trail runs out of La Crescent, crosses the backwaters, and ends at the Sportsmen's Boat Landing beside US 14/61. The City of La Crosse's project page still lists construction on the last link for "Fall 2026 through Fall 2027." The newest planning documents now put the work in 2027.

La Crescent finished its part of the job a while ago. The remaining mile is a Wisconsin project, and the dates on it have moved.

Where the trail stops today

La Crescent spent more than two decades on this trail. The Root River Trail Extension plan, adopted in June 2024, says the Wagon Wheel Trail in La Crescent "took 21 years from conception to completion." The final piece was the bicycle and pedestrian bridge over US 14/61, built as Phase 3. A state Senate announcement put the total cost at $3.5 million: $2.5 million from the 2018 state bonding bill and a $1 million grant from MnDOT, and dated the ribbon cutting to September 2022. The 2024 extension plan gives 2023 as the year the bridge was built, so the two sources disagree on the date.

The bridge is 162 feet long and carries a 10-foot shared-use path. Its spiral ramp wraps around a stormwater detention pond between city streets, according to the engineering firm WHKS. Past the bridge, the trail is a mix of paved and gravel surface. Part of it runs next to the Upper Mississippi River National Wildlife and Fish Refuge, as the Explore La Crescent trail page describes it.

It ends at the Sportsmen's Boat Landing. WXOW describes the landing as where "the current Wagon Wheel Trail ends." The bridge was meant to link La Crescent to La Crosse, and on the Minnesota side it does. On the Wisconsin side, the connection hasn't been built yet.

The missing mile is a Wisconsin project

The City of La Crosse is leading the connector. Its project page describes a shared-use path about one mile long on the north side of US 14/61. It would start at the Sportsmen's Boat Landing and meet the existing path under the Cass Street and Cameron Avenue bridges over the Mississippi's main channel. The plan calls for a 10-foot asphalt path. Where it crosses the West Channel on the westbound US 14/61 bridge, the path would be a 14-foot concrete bridge deck.

The West Channel crossing has been described more than one way. The City's capital budget, adopted in August 2025, describes a separate pedestrian and bicycle bridge built next to the existing highway bridge. The two documents don't match. Either the design changed between them, or the details are still being worked out.

For now, people get between the two cities along the highway itself. WIProud reported in April 2024 that cyclists use the shoulder of US 14/61 and that the existing sidewalk is narrow. At a public meeting that spring, La Crosse Planning Manager Tim Acklin called the narrow shoulder and inadequate sidewalk unsafe, WIZM reported.

Three newer schedules point to 2027

The City's page says construction runs "Fall 2026 through Fall 2027." It lists the project phase as "Final Design," and the page has no date. Three other sources all put construction later, and the two that carry dates are from August and October 2026.

Source What it says Date of source
City of La Crosse project page Construction Fall 2026 through Fall 2027 Undated
WisDOT STIP snapshot Schedule date of 07/13/2027 for project 5991-07-73 August 2026
WXOW mayor's ride report Bridge construction "set to begin in September 2027" Undated, recent
LAPC 2027–2030 TIP "Construction Anticipated in 2027-2028" Approved October 21, 2026

The La Crosse Area Planning Committee approved its Transportation Improvement Program on October 21, 2026. That's the most recent dated source, and it lists the Wagon Wheel connector for 2027 and 2028. The WisDOT date and the WXOW date both fall in the second half of 2027, which fits that window. So at least by these schedules, the leaves will fall this year with no trail construction along US 14/61.

All of these dates are programmed schedules, not commitments. A start date isn't firm until a contract is let and work begins.

The cost has gone up

Cost is part of why the schedule matters. In 2024, WIZM reported Acklin's estimate of roughly $7 million for the overall cost. The City's budget narrative, adopted in August 2025, forecast about $6.9 million. Roughly $4 million of that was WisDOT Transportation Alternatives Program funding, and the City was still looking for grants to cover about $1.9 million.

The October 2026 TIP lists the project at $8,359,787. The federal share is $4,010,400, and the local and other share is $4,349,387. The federal amount is the same $4,010,400 WisDOT awarded to the City's "Wagon Wheel Trail Link" in its 2022–2026 TAP round. That federal share hasn't changed while the total has. Between the 2025 forecast and the 2026 TIP, the project grew by more than $1.4 million, and the local side now carries more than half of it.

For residents, this is the main thing to watch. A fixed grant paired with a growing total puts more of each delay's cost on the local budget. The City's adopted 2026–2030 capital budget already planned $4,020,500 in borrowing for the project, alongside the federal grant.

What the connection is supposed to do

On the Minnesota side, support has been steady. On the mayor's annual bike ride, which crossed into Minnesota, La Crescent Mayor Mike Poellinger described the connector to WXOW this way:

"It's a multi-use trail and what it does is it gives them an opportunity to go to downtown La Crosse and it gives people an opportunity from La Crosse to come into La Crescent. And they may not have done that in the past just because there wasn't a good safe connection."

He's describing travel both ways. La Crescent has already paid for its half. When the Wisconsin mile opens, people from La Crosse will have a path into La Crescent's trail system, and the Phase 3 bridge will be part of a route that runs all the way through.

What's next on La Crescent's own list

Once the connector is built, the next questions are about La Crescent's own projects. Each one sits at a different stage.

  • Wagon Wheel Phase 4. La Crescent's Park and Recreation Commission minutes from February 2, 2026 note an update on the "Wagon Wheel phase 4 improvement project." The minutes don't include a route, timeline, or funding. The LAPC TIP lists Phase 4 as an illustrative project for 2026–2040 at an estimated $1,160,000. The TIP says that list shows possible future improvements, not a committed schedule.
  • Root River State Trail extension. The same illustrative list puts a trail linking La Crescent, Hokah, and Houston in 2035–2045 at $9,000,000. The 2024 extension plan said there was no funding yet for land acquisition.
  • Wagon Wheel Bridge to Miller's Corner. The 2024 plan supports seeking federal money for a separate multi-use path along this stretch. An earlier application for the section to S. 14th Street wasn't funded.

The 2024 plan's own comparison sets expectations. The Wagon Wheel took 21 years, and talks about finishing the Root River State Trail have gone on for more than 40.

Using the trail this fall

The trail is open now as far as the landing. Paper trail maps are available at City Hall, the library on Main Street, the La Crescent Chamber office at 111 S Walnut Street, and the La Crescent Historical Museum at 328 S 3rd Street. The upkeep is partly done by community members. A February 2026 city committee record lists buckthorn removal on the Wagon Wheel Trail among the 2025 volunteer projects.

When construction does start on the connector, La Crosse expects to keep traffic moving with single westbound lane closures on US 14/61. Under the current schedules, those lane closures are a 2027 issue.

Some people choose between La Crescent and the Wisconsin side of the river partly by how easy it is to get across. A trail link whose schedule has moved can matter in that choice. If you'd like to talk through how the river crossing fits into everyday life on either bank, Jake Ramey is glad to help. Let's Connect.

Work With Jake

Partner with a La Crosse area REALTOR® who's as invested in this community as you are. Jake puts your goals first and delivers results every step of the way.

Follow Me on Instagram